C. STEINWEG OMAN LLC · OPERATIONS STANDARD & TRAINING · PORT OF SOHAR

Proactive Vessel Supervision & Shared Ownership

Think ahead. Take responsibility. Do it together — SV4 to SV1.
SOP-OPS-01Document
Rev 1Merged & expanded
All Supervisors & ForemenApplies to
RoRo · Break Bulk · Project Cargo · Dry BulkScope
Operations ManagementOwner

1Purpose

This standard sets one expectation for everyone on the operation: think ahead, take responsibility for your part, and do it together. The work we handle is largely repetitive and predictable — across RoRo, break bulk, project cargo and dry bulk, the same gear changes, equipment moves, lashing tasks and cargo handovers recur on almost every vessel.

Because the sequence is predictable, the resources it needs can and must be prepared in advance — not arranged at the moment they are needed. A supervisor is paid to be one step ahead of the operation, not to follow it.

If you can see it coming, it should already be there.

2Thinking Ahead — Anticipate · Stage · Confirm

Being proactive is not a feeling — it is three concrete steps, on every shift, on every vessel, whatever the cargo.

1

Anticipate

Read the stowage plan, cargo sequence, ramp/lashing plan and crane progress. Ask one question constantly: what will be needed in the next hour?

2

Stage

Bring the gear, equipment, documents or people to the point of use before they are required — so there is zero waiting when the moment comes.

3

Confirm

Check what you staged is correct, complete and serviceable — right slings, right SWL, certified, inspected, fuelled — before it is called for.

3Why It Pays — and What It Costs If You Don't

The reason we work ahead is simple: standing time is the most expensive thing on the quay. A crane that stops still costs full berth, gang and equipment money — for nothing produced. The small effort of preparing ahead is far cheaper than the wait it prevents.

IF YOU DON'T — the cost
The crane stops and the whole gang stands idle — paid time, zero output.
Productivity (moves/hour) drops and the vessel takes longer at the berth.
Segregation and document errors surface only after cargo is mixed.
Problems land on the next shift, and on the SV above you.
The client sees a slow, reactive operation — it costs us reputation and repeat business.
IF YOU DO — the benefit
The crane and ramp keep moving — every prepared minute is a produced minute.
Higher moves/hour, shorter berth stay, more vessels handled.
Mistakes are caught before they happen — safer, cleaner operation.
Each shift is handed over prepared, not mid-problem.
The client sees a professional, in-control terminal — that wins the next call.

4Responsibility — Who Owns What

Proactivity is only real when everyone owns their part. Too often the preparing waits on the top. The standard is that responsibility runs all the way down the line, and each level thinks ahead and prepares within its own span. We do it together.

SV4The terminal
Owns the whole terminal — all berth positions. The commanding, overall view: looks across every vessel and berth, coordinates and directs resources between them, and makes sure no berth is left short. Thinks a shift ahead for the terminal, not just one ship.
▼ prepares & owns within its span
SV3 & SV2A specific vessel
Own their vessel from berthing to sailing. Read the stowage & cargo plan, sequence the holds/cranes/decks, and stage gear, equipment, documents and crew ahead of every change on that ship. They don't wait for SV4 to arrange what they can see coming.
▼ prepares & owns within its span
SV1Hatch foreman
Owns the hatch & crane in front of him. The front line of anticipation: sees the parcel finishing, the hold clearing, the gear about to change — and has the next thing rigged and ready before it is called. Nothing foreseeable stops his crane.
Everyone anticipates, stages and confirms within their span. The higher level sets direction and supports; it does not do the preparing that a lower level can already see coming. That is what "together" means.

5Keeping the Standard — Plan · Do · Check · Act

Proactive supervision is not a one-off; it is a habit we keep sharp with a simple improvement loop — PDCA. Run it on every shift and every vessel.

PLAN

Before the shift, read the operation and plan the next hours: what gear, equipment, documents and crew each stage will need, and when.

DO

Stage it ahead of time and run the operation — every level preparing its own span so the crane and ramp never wait.

CHECK

Watch what actually happened: did anything cause standing time? Was a foreseeable need not prepared? Confirm gear was correct and serviceable.

ACT

Fix it and lock it in: brief the next shift, agree the lesson together as a standard, and adjust so it doesn't happen again. Then plan the next round.

Plan → Do → Check → Act → and round again. Every avoidable stop we catch once becomes a stop we never have again.

6Own Your Span

Whatever level you sit at, you own the terminal, vessel, hatch or task assigned to you for the whole shift. Owning it means:

It doesn't stop on your watch

Nothing foreseeable and preparable should ever stall your crane, ramp or gang.

You account for what's missing

"I was waiting for it" is not an answer for a predictable need in your span.

You act first

Read the operation and move — don't wait to be told by the controller, chief or the SV above you.

A reactive supervisor manages problems after they appear. An owner prevents them — at every level. We expect owners, and we own it together.

7Application

Think ahead. Take responsibility. Do it together — and be the supervisor who is already there.

Acknowledged by (name & grade)
Signature
Date
C. Steinweg Oman LLC · Port of Sohar · Operations SOP-OPS-01 · Rev 1 · Proactive Vessel Supervision & Shared Ownership